Table 1

Summary of main activities for project preparation, design and implementation [8].

Phase Dates Sub activities
I November 2009–June 2010 Obtaining financial resources; literature review on technological options; site visits to four potential communities; wind and solar resource assessments; selection of the Boca de Lura community as project beneficiary; pre designs.
II June 2010–May 2011 Detailed technical design; permit requests to relevant institutions; laboratory tests on system components and generators before installation; installation at site and commissioning of the hybrid system.
III May 2010–January 2011 Follow up measures, including technical inspections of the system and training sessions for end-users; dissemination of results to academia and the public.

Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.

Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.

Initial download of the metrics may take a while.